Cancún, Quintana Roo — Construction of the Kukulcán road distributor in Cancun’s Hotel Zone is 33% complete, according to the Ministry of Infrastructure, Communications and Transport (SICT). The project, a complement to the Nichupté Vehicular Bridge inaugurated in May, has an investment of 484 million pesos ($26 million USD).
Work is currently focused on raising columns, asphalt foundations, soil compaction, and developing piles, footings, and reinforcing steel. Underground infrastructure for drinking water and drainage networks is also underway.
The 1.92-kilometer distributor will include a 0.77-kilometer elevated structure. Officials say it will benefit 1.3 million residents and millions of tourists who visit the destination each year.
Construction is taking place within existing rights of way on Boulevard Kukulcán, affecting axes 100, 200, 80, 60, and 70, as well as part of the Nichupté bridge right of way. The SICT expects to complete the work by the end of October, weather permitting.
More Development
- Pollution Blocks Diving in Tulum Cenotes, Instructor José Urbina Warns
- Quintana Roo Officials Warn of 21 Illegal Real Estate Developments in Playa del Carmen
- Quintana Roo to Finish 67 School Canopies in 2026 With 240 Million Pesos
- Quintana Roo Flags 18 More Irregular Real Estate Developments in Isla Mujeres
- Infonavit Opens New Service Center in Cancún to Assist 15,000 Workers a Year
More Cancun
- Can Cancun Win Winter Back? Flights and Flexibility Hold the Key
- Canadian Tourists Flock to Mexico as U.S. Visits Drop
- Quintana Roo Restaurants Face 55 Closures, 500 Job Losses
- Cancun Airport Lines Up 443 Flights for October 31
- Boat Noise Is Drowning Out the Natural Sounds of Mexican Caribbean Reefs, Researchers Warn