Isla Mujeres, Quintana Roo — The modernization of 4.2 kilometers of the Cancún-Isla Blanca corridor is 37 percent complete and scheduled for completion in December, according to Mexico’s Infrastructure, Communications and Transportation Secretariat (SICT).
The work is taking place between kilometer markers 7+000 and 11+200 on the mainland side of Isla Mujeres, where the road is being widened to two lanes in each direction. The project also includes a bicycle lane, sidewalks, street lighting, and horizontal and vertical signage, the federal agency said.
The section currently under construction has a roadway width of approximately six meters. Work began in March and is now focused on earthworks, drainage and paving, along with complementary and related works. SICT said environmental monitoring and mitigation measures are also being carried out during construction.
The project is expected to benefit about 22,600 residents in the northern part of Quintana Roo and generate 1,320 direct and indirect jobs. It is part of a broader set of improvements along the corridor connecting Cancún to the Isla Mujeres mainland and the tourist developments toward Isla Blanca.
More Development
- Sheinbaum Announces More Gas and Power Grid Upgrades for Quintana Roo
- Quintana Roo Plans 4.4 Billion Peso Wind Farm in Othón P. Blanco
- Cozumel Prison Expands Capacity by More Than 50% With 80 New Spaces
- Yucatan Debuts Southeast Mexico’s First Cyclotron for Precision Oncology
- Cancún Shuts Down Two Gated Developments for Selling Lots Without Permits
More Cancun
- Five Men Sentenced To Up To 50 Years For Killings In Cancún And Felipe Carrillo Puerto
- Two Women Rescued From Human Trafficking in Cancún Search Warrants
- Cancún Restaurant Sector Welcomes Extended Hours in Hotel Zone
- Man Who Posed as Inspector to Extort Cancún Merchant Ordered Held Two Years
- 272 OXXO Stores in Cancún Join ‘Purple Points’ Safety Network